Cultural and Creative Industries Development Agency
Entertainment Special Effects Licensing Authority
Guidance Notes No. 6
Risk Assessment and Method Statement for Large Scale Special Effects Scenes
For special effects scenes or pyrotechnic displays of large scale, applicants shall make arrangement to conduct a Risk Assessment and work out a Method Statement with regard to the events. These documents shall be submitted together with the application for a discharge permit to the Entertainment Special Effects Licensing of Authority for consideration.
A. Risk Assessment
A Risk Assessment shall cover all operations associated with the various stages during the life cycle of the special effects materials including conveyance, storage, setting-up, discharge, handling of misfires and surplus dangerous materials. A Risk Assessment shall include three key processes:
(1) | Hazard identification – | for each activity, identify all the potential hazards associated with the proposed special effects materials. Consideration must be given to the actual site conditions, the equipment, vehicles, and vessels actually used, and taking note of all peculiar features, hazardous installations, overhead structures/machines, hospitals, aged homes in the vicinity. |
(2) | Risk evaluation – | with respect to each hazard identified, evaluate the likelihood of occurrence and the consequence if it occurs. Risk is the product of likelihood of occurrence times the consequence. |
(3) | Risk control – | for any risk high than the acceptable level, proposed mitigation measures to reduce the risk to an acceptable level. |
In general, risk mitigation measures may include:
Given in the Appendix is part of a listing of the activities and the corresponding risk control measures associated with the staging of pyrotechnic displays at sea. It should be noted that this listing is not comprehensive and is given here as a guidance only. Applicants are required to produce a full Risk Assessment report covering all the hazards associated with all the activities that may be encountered, taking account of the actual conditions of the site, the special effects materials used, and the work procedures adopted.
B. Method Statement
A Method Statement is a detailed description of work procedures for accomplishing all tasks and activities required for staging a special effects event. The Method Statement should be worked out having regard to the actual site conditions and the actual resources to be employed (i.e. the actual vehicles/vessels and the minimum number of special effects operators/assistants to be employed, etc.).
C. Relation between Risk Assessment and Method Statement
The procedures mentioned in the Method Statement should tie in with those discussed in the Risk Assessment, especially those referring to the deployment of resources or measures to mitigate the risks. In fact, from the results of a Risk Assessment, we should be able to identify the areas that need to be addressed in details in the Method Statement.
In view of the inter-relationship mentioned above, it is therefore essential that the Risk Assessment and the Method Statement should be submitted to this Authority at the same time. It is no point for this Authority to comment on either document, without referring to the other document.
Besides, if the applicant subsequently decides to change the work procedures or use alternative resources to accomplish a particular activity, the applicant should review the Risk Assessment to verify if the results are still applicable to the proposed changes. (This Authority's approval is required prior to implementing any changes to the work procedures.)
The Method Statement submitted by an applicant will be treated as part of the licensing conditions and will be attached to the relevant permits. Consequently, it will have a binding effect on the holder of the permit and other concerned parties (such as the licensed special effects operators). It is therefore compulsory for the holder of the permit and all concerned parties to comply with the Method Statement, in addition to the terms and conditions specified in the permits.
Entertainment Special Effects Licensing Authority
1 July 2022
ESELA Guidance Notes 6 (1.7.2022)
Appendix
Entertainment Special Effects Licensing Authority
Notes for Conducting a Risk Assessment
As a guidance, the following steps may be taken in preparing a Risk Assessment report:
(1) Examine in details the activities associated with the proposed work.
(2) For each activity, work out the work procedures having regard to the actual site conditions, and the materials and resources to be employed.
(3) List out all the activities and work procedures in a logical manner to form a Method Statement.
(4) From the Method Statement, identify all the potential hazards associated with each activity and the work procedures.
(5) For each hazard, evaluate the likelihood of occurrence and the consequence.
(6) Consider risk control measures to mitigate the risk.
(7) Repeat steps (4) to (6) for the next activity.
Given below as an example is part of a list of activities associated with the staging of pyrotechnic displays in the harbour. It should be noted that this listing is not comprehensive and is given here as a guidance only. Applicants are required to produce a full Risk Assessment report covering all the hazards associated with all the activities that may be encountered, taking account of the actual conditions of the site, the special effects materials used, and the work procedures adopted.
Activity | Risk Control |
---|---|
A. Loading/unloading of PSEM at WDGA – Take note of all factors including:
|
Risk control measures may include:
|
B. Stowage of PSEM at WDGA – Take note of all factors including:
|
Risk control measures may include:
|
C. Setting-up of PSEM at WDGA – Take note of all factors including:
|
Risk control measures may include:
|
D. Test of Circuits hooked up with PSEM – Take note of all factors including:
|
Risk control measures may include:
|
E. Conveyance of the installed PSEM to the firing venue – Take note of all relevant factors. |
List out all appropriate risk control measures. |
F. Anchoring/Sleeping at the firing venue – Take note of all factors including:
|
List out all appropriate risk control measures. |
G. Firing of the PSEM – Take note of all factors including:
|
Risk control measures may include :
|
H. Checking/handling of Misfires and Unused PSEM – Take note of all relevant factors. |
List out all appropriate risk control measures. |
I. Labelling of PSEM – Take note of all relevant factors. |
List out all appropriate risk control measures. |
J. Other relevant activities – List out all other relevant activities and take note of all factors. |
List out all appropriate risk control measures. |